Science Building (SI
2399 Euclid Avenue )
Project Number: LF-1104A

 

Current Status:

Design

Description of Work

South West corner of the Science Building constructed circa 1967. Science Building Wall at South West steps. Repair and reconstruct brick fascia separated from wall, a failing beam support, degraded exterior steps and the exit door.

Contract Bid scheduled for Spring 2012

 

Budget

Project Budget: $600,000
Construction Budget: $ 178,750

 

 

 

Project Team

Planning Consultants:
Barber & Hoffman, Inc

CSU Staff
Project Manager: Hugh Holley

University Architect: Ed Schmittgen

Financing: 

Local Funds

Last Updated: October 2011

engaged learning
Mailing Address
Cleveland State University
2121 Euclid Avenue, PS 235H
Cleveland, OH 44115-2214
Campus Location
Plant Services, Room 235
1802 East 25th Street
Phone: 216.687.5121
Fax: 216.687.9227
architect@csuohio.edu


This site contains files that require the free Adobe Reader to view.